Sited off the coast of Blyth on the North East coast. These are 5 test modules for EDF energy. BAM Nuttall constructed these in a dry dock on the Tyne. Filled with heavyweight self compacting concrete and then moved to position from Wallsend up the Tyne to South Shields.
Work was completed over a period of 2 months due to site issues which delayed work.
4500m3 of bespoke Topflow product was used during the construction.
Customer: BAM Nuttall